MSCPA and its member companies, Geneva Pipe and Precast and Oldcastle Infrastructure, are excited to present monthly profiles of project achievements in the Utah and Idaho area. We hope that these projects will help inspire engineers in our market to come up with unique and original solutions to their civil engineering design problems.

At the end of the year, we will be awarding a 2021 MSCPA Project Achievement Award to one of the projects highlighted each month. If you have a project that you think should be considered for a profile, please email us a msconcretepipe@gmail.com.

MONTHLY PROJECT ACHIEVEMENT PROFILES:

 JANUARY 2021 – Baker Canyon Wildlife Underpass (I-15)
Owner: Utah Department of Transportation (UDOT) and Utah Division of Wildlife Resources (DWR)
Contractor: W. W. Clyde & Company (General), Harward & Rees (Subcontractor)
Engineer: Avenue Consultants and UDOT Structures Group
Manufacturer: Geneva Pipe and Precast
Overview: To improve the safety of I-15 for both animals and motorists, our team manufactured and installed 40 three-sided box culvert sections to create a 24-foot span wildlife underpass for Baker Canyon between Mile Post 135 and 142.5.

CLICK HERE FOR FULL PROJECT PROFILE!
 February 2021 – Trail Mountain Watershed Project – Rilda Canyon, Huntington UT
Owner: Emery County, Utah
Contractor: Perco Rock
Engineer: Johansen & Tuttle
Manufacturer: Oldcastle Infrastructure
Overview: This project included the installation of a 20′ x 10′ precast box culvert diversion structure, large wing walls, and a debris structure installed in Rilda Canyon, a smaller canyon in the Huntington Canyon area. 
CLICK HERE FOR FULL PROJECT PROFILE!
March 2021 – The Northshore Project – Saratoga Springs, UT
Owner: Saratoga Springs City (Developer: D.R. Horton)
Contractor: Noland & Sons; Mitchell Excavating
Engineer: LEI Consulting Engineers
Manufacturer: Geneva Pipe and Precast
Overview: This project included the installation of 8,352 feet of 36″ RCP, over 5,000 feet of 15″ RCP, and 4,060 feet of 7′ x 3′ box culvert in the Northshore development project on Utah Lake in Saratoga Springs, Utah. 

CLICK HERE FOR FULL PROJECT PROFILE!
April 2021 – Stansbury Park Hwy 138 Pedestrian Underpass – Stansbury Park, UT
Owner: City of Stansbury Park / Stansbury Park Service Agency
Contractor: Stapp Construction
Engineer: Triton Engineering
Manufacturer: Oldcastle Infrastructure
Overview: This project was designed to allow the residents of Stansbury Park to safely cross under Highway 138 from the North and South. It included installation of 26 pieces of 12′ x 9′ box culvert.

CLICK HERE FOR FULL PROJECT PROFILE!
May 2021 – 400 South & I-15 Pedestrian Underpass – St. George, UT
Owner: St. George City / UDOT / Dixie State University
Contractor: American Civil Constructors
Engineer: Horrocks Engineers
Manufacturer: Geneva Pipe and Precast
Overview: This pedestrian underpass under I-15 connects the Dixie State University campus to the student housing and buildings on the east side of the freeway. It included installation of 204 feet of arched three-sided precast 16′ x 11′ box culvert.

CLICK HERE FOR FULL PROJECT PROFILE!
June 2021 – Park Valley Commercial – South Jordan, UT
Owner: Peterson Development
Contractor: Salt Lake Excavating
Engineer: Anderson Wahlen Associates
Manufacturer: Oldcastle Infrastructure
Overview: This project included the installation of over 1,400 linear feet of reinforced concrete pipe. In order to handle the runoff from the development, the design called for 60-inch, Class III pipe.

CLICK HERE FOR FULL PROJECT PROFILE!
July 2021 – Springwater Storm Drain – Orem, UT
Owner: Orem City
Contractor: Tri-Co Realty & Investments
Engineer: City of Orem Engineering Division
Manufacturer: Geneva Pipe and Precast
Overview: This project included the installation of one 10-foot diameter storm water separator, two large diameter manholes, a custom 7′ x 7′ vault, 492 linear feet of 54-inch RCP, 176 linear feet of 48-inch RCP, and 88 linear feet of 24-inch RCP. This project was designed and installed to prevent localized flooding in developing residential and commercial areas in west Orem.

CLICK HERE FOR FULL PROJECT PROFILE!
August 2021 – Little Bear River Box Culvert – Wellsville, UT
Owner: Wellsville City
Contractor: Legrande Johnson
Engineer: Jones and Associates
Manufacturer: Oldcastle Infrastructure
Overview: This project replaced a 100+ year old one-lane bridge over the Little Bear River and included the installation of seven sections of 29′ x 15′ three-sided, precast concrete box culvert and precast concrete footings.

CLICK HERE FOR FULL PROJECT PROFILE!
September 2021 – Coming Soon…
October 2021 – Salt Lake International Airport Cargo Apron and Taxiway
Owner: Salt Lake International Airport
Contractor: Ames Construction
Engineer: JViation
Manufacturer: Oldcastle Infrastructure
Overview: This project installed over 6,000 feet of Class V reinforced concrete pipe ranging in size from 18-inch to 54-inch diameter, two 7′ x 9′ precast concrete utility meter vaults, and an oil/water separator in an 8′ x 16′ precast concrete vault.

CLICK HERE FOR FULL PROJECT PROFILE!
November 2021 – Coming Soon…
December 2021 – Twin Falls Idaho Subaru Canal Piping Project
Owner: Subaru of Twin Falls, Idaho
Contractor: J5 Construction
Engineer: EHM Engineers
Manufacturer: Oldcastle Infrastructure
Overview: In order to expand development in the area west of Twin Falls, the Subaru dealership chose to pipe an existing gravity irrigation canal with over 1,100 feet of 48-inch Class III reinforced concrete pipe.